test

Test Day

Well, that was interesting. I took the trike to the Exeter VOSA station for its MSVA test, and which I have been stressing about for the last 3 months, and which didn’t quite go to plan.

, , ,

That Final Push – Day 4

Today I managed to finish one of the jobs that I started last week, and that was the mudguards. I made a decision 2 weeks ago to postpone the test till 26th July. this is due to the fact that progress was to slow and the outstanding jobs where to great to make it to test […]

, , , , , , ,

With Great Power (part 5)

After all the fun we had trying to start the engine last time, we thought we would attempt it again, following installing some of the wiring for the trike. This time it was a huge success!!

, , , , , ,

Hanging on

As the build has been progressing and with the completion of the engine, I decided I needed to check the fitting of some of the components, mainly the handbrake and front forks. With the help of my friend Dan, we got to work.

, , , , ,